2005-10
The only package in NHAI in Orissa
was finally completed in Jun 06 and I stayed one more month upto Jul 06.
In the month of Mar 06, I got an
offer of a top job in Keonjhar Infrastructure Dev Co, which I differed by 3
months, and finally joined on 1 Jul on part time basis and 1 Aug on full time
basis. The new company sent me on a foreign trip to Germany to negotiate with a company
Wirtgen for supply of machines on hire, which I succeeded, but with foam
bitumen road. Since we decided for a concrete road further negotiation were
done by our eminent Vice Chairman and deal was through. This road is only 28 Km
two laning on NHAI standard on a village road which is for mining trucks loaded
with 20 t load, and was in a dilapidated state.
After several changes latest was
to build a Foam bitumen layer over which a Continuous concrete pavement will be
laid. This is the first time in India
with foam bitumen and only composite pavement of bitumen and concrete. Since no
major contractor was willing to do the work, we had to award to a local one
without tender for the base work and CD works numbering 85.
Simultaneously I got an offer of
Resident Engineer for the longest rail bridge of the state in a consultancy
SOWiL- Halcrow JV and did join on 21 Aug. I used to commute daily to Jagatpur
just across Cuttack
and work was very interesting. The days when I go to the Keonjhar I used leave
without pay.
This is the 2nd rail
bridge across Mahanadi and of a length of 2.1
Km longest in the state. Gammon India
was the contractor for substructure in the conventional well foundation except
one with caisson. The change on the original drawing is of the abutment at Cuttack side, where a road
is passing under the last span. For this I had to design a retaining wall on
the approach of the embankment.
The superstructure is of open web
girder and the contractors are BBJ.
The numbers of spans are 32 each
of 65.84 m. and the entire fabrication by welding cum riveting was done at the
site as against the railways pattern of fabricating at workshop and
transporting to site. The erection was by incremental launching with one anchor
span erected on the left approach embankment. The connection between the anchor
span and span to be erected is by a linking specially designed, which is
repeatedly used for subsequent spans.
The design consultants have
completed their job before tendering. All the changes has to be done at site. I
found this an opportunity in picking up CAD operation in the computer, so that
I do not depend on the project office. My personal contribution was complete as
far as the CRC road diversion on Cuttack side with necessary changes in
abutment design, new design of huge retaining walls and reducing the depth of
sinking from -32 to -20, ie 12 meters.
Working with railway engineers
with their inflated egos was difficult, but eventually they accepted that I
know the job.
Meanwhile Keonjhar project was
stopped due to non contribution of stakeholders share and non availability of
loans from the banks. I approached ILFS for finance and they have become our
PMC in place of the one SM Consultants. They succeeded in getting a contractor fixed.
Meanwhile the other job of Rail Bridge
was going so fast, that ADB, RVNL were of the opinion that this is only project
which is in time and cost. A lot of people visited the site including MoS Railways
Mr Velu.
On the Keonjhar side government
called a meeting and threatened to take away the work. I resigned the job of
CEO, but was kept as an Advisor chargeable to OSIL instead of Kidco effective 1
Mar 08.
Even though the bridge proper was completed in
time the track laying both on the bridge and approaches took a long time. These
works are sub let to 2 parties, who have no resources, and therefore RVNL took
direct charge in order to expedite. The supply of SEJs and channel sleepers
with fittings were also delayed. Ultimately the double engine passed through at
10,20and 30 km/h for testing of deflection and lateral shift on 1 Jul 08.
The Commissioner of Railway Safety
gave the clearance on 18th Jul and trains started running from 19th,
the fastest ever in Railways. The Chairman of Railway Board formally
inaugurated and flagged off on 26th stating that this project has
been completed with no time or cost overrun and congratulated RVNL, consultants
and the contractors on excellent quality work with good progress.
My services came to an end on 31
Dec 08, but was asked to continue. Then a bombshell fell on 14 Jan 10 of non
approval of the extension. Meanwhile the Project Manager at Bhubaneswar
resigned and finally left on 1 Apr 09, and I was asked to look after the job
till July end for Mahanadi and KT projects.
The approval was however was for Mahanadi
only, in order to make the final bill, variation statement etc. There was a
further extension upto end of Aug, for which the salary was not paid by SOWiL yet.
I completed all the above except handing over the documents and equipment to
RVNL.
The above period was under Jupiter’s
4th house aspect. It shifted to 5th house on 19 Dec 09
and my interview for the next assignment was on 20 Dec at Pal Height. Posting
for the post of Construction Engineer in Meinhardt Singapore Pte Ltd at Bhubaneswar
came on 22nd and I joined on 23rd.When I approached the
clients OWSSB, they asked for approved cv and a letter from the company. This
continued till 15th Jan. Team Leader joined on 20th and
real work started in Feb 10.The name of the project was Integrated Sewerage
system under 12th Finance Commission and JnNURM for 6 sewerage
districts.
The construction work was awarded
2 years back to ECCI Chennai,for dist I, II, III,which we are to supervise,
along with additional work of survey, design and execution for the remaining
districts.
After a long time I was the first
to join and there was no office, and the clients refused to accept me since
there is no official communication from the company. This continued for a
fortnight after which there was a semblance of activities. A chap came from
head office for fixing a house for office which was under construction, which
we could occupy only on 10 Feb, 10.fans could come by 20 Mar 10.Salary comes in
installments that too for a foreign company.
Finally I gave a notice ending on
31 Jul 10, while the company released on 31 Aug 2010.
Then another Sen of the Railways
forced one co McML System Pvt Ltd to take me as a Project Manager for 3rd
railway line from Jakhapura to Haridaspur with hq at Badachana.I worked there
from 1 Nov to 16 Nov and left due to food and other logistic problem.
Finally after 15 years post
retirement work, I hope I finally retired but not tired, and am existing but
not living a meaningful life.
AWS Training Institute in Delhi
ReplyDelete